Rehabilitation Of Multi Purpose Hall








ORGANISATION DETAILS
Organisation Name: BARANGAY MAMBAJAO - MAASIN CITY SOUTHERN LEYTE
Address: RAMON AMORA BUYSER
BAC CHAIRMAN
R. KANGLEON STREET
Maasin City
Southern Leyte
Philippines 6600
63-53-5702846
63-966-4120972
mambajaomaasincity@gmail.com+63-63-53-5702846


PREQUALIFICATION DETAILS
Document Type: Tender Notice
Bidding Type: Not Specified
Project Location: Philippines
Tender Notice No: 9688175
Description: Invitation to bid (itb) :rehabilitation of multi purpose hall

1. general requirements
Project billboard/signboard 1.00 lot 5,550.00 5,550.00
Contract close-out 1.00 lot 4,000.00 4,000.00
Mobilization 1.00 lot 3,000.00 3,000.00
Total item cost: 12,550.00
2. removal of dilapidated materials a= 49.00 sq.M.
Labor
1 construction foreman 12.00 day 550.00 6,600.00
2 skilled worker 12.00 day 450.00 10,800.00
4 laborer 12.00 day 350.00 16,800.00
Labor cost : 34,200.00
Total direct cost : 34,200.00
Ocm 5,130.00
Profit : 3,420.00
Tax 2,137.50
Total item cost : 44,887.50
Unit cost/sq.M.: 916.07
3. scaffolding q= 1.00 lot
Materials:
30 pcs - 2x2x3x12 coco lumber 180.00 bd-ft 30.00 5,400.00
30 pcs - 2x2x12 coco lumber 120.00 bd-ft 30.00 3,600.00
Assorted common nails 15.00 kls 75.00 1,125.00
Item cost : 10,125.00
Labor
1 skilled worker 3.00 day 450.00 1,350.00
2 laborer 3.00 day 350.00 2,100.00
Labor cost 3,450.00
Total direct cost: 13,575.00
Ocm 2,036.25
Profit 1,357.50
Tax 848.44
Total item cost: 17,817.19
Unit cost/lot 17,817.19
4. ceiling works a= 61 sq.M.
Materials
Marine plywood 4 x 8 x 1/4" 26.00 sheet 550.00 14,300.00
91 pcs - 2" x 2" x 12 good lumber ceiling joist 364.00 bd.Ft 65.00 23,660.00
2" x 2" x 10" ceiling moulding 20.00. pcs 375.00 7,500.00
Assorted common nails 20.00 kgs. 75.00 1,500.00
Material cost: 46,960.00
Labor
1 skilled worker 14.00 days 450.00 6,300.00
2 unskilled worker 14.00 days 350.00 9,800.00
Labor cost: 16,100.00
Total direct cost: 63,060.00
Ocm 9.459.00
Profit 6,306.00
Tax 3,941.25
Total item cost: 82,766.25
Unit cost/sq.M 1,356.82
5. painting works a= 61.00 sq.M.
Materials
Liquid tile primer (2-coats) 12.00 gals. 850.00 10,200.00
Latex paint semi-gloss (1-coats) 6.00 gals. 950.00 5,700.00
Reducer 6.00 gals. 850.00 5,100.00
Quick dry enamel(for moulding) 2.00 gals. 850.00 1,700.00
Paint thinner 2.00 gals. 500.00 1,000.00
Glazing putty 10.00 gals. 850.00 8,500.00
Epoxy non-zag 10.00 litr. 850.00 8,500.00
Sand paper (assorted) 40.00 pcs 30.00 1,200.00
Scraper 6.00 pairs 150.00 900.00
6 roller 2/pan 3.00 sets 150.00 450.00
6 roller 4.00 pcs. 75.00 300.00
Paint brush #3 6.00 pcs. 80.00 480.00
Paint brush # 2 4.00 pcs. 60.00 240.00
2" masking tape 10.00 pcs. 80.00 800.00
Material cost: 45,070.00
Labor
2 skilled worker 7.00 day 450.00 6,300.00
4 laborer 7.00 day 350.00 9,800.00
Labor cost: 16,100.00
Total direct cost: 61,170.00
Ocm 9,175.50
Profit 6,117.00
Tax 3,823.13
Total item cost: 80,285.63
Unit cost/sq.M.: 1,316.16
6. glass door and sliding windows q= 1.00 lot
Materials
One-way glass door with door closer(2.1 x d1 0.90m) 1.00 sets 8,360.00 8,360.00
6mm thick dark grey glass sliding window w1 aluminum (1.2 x 1.2 m) 2.00 sets 13,090.00 26,180.00
6mm thick dark grey glass sliding window w2 aluminum (1.77 x 1.17 m) 2.00 sets 16,720.00 33,440.00
6mm thick dark grey glass sliding window w3 aluminum (1.82 x 1.15m) 2.00 sets 16,720.00 33,440.00
Material cost 101,420.00
Labor
2 skilled worker 4.00 day 450.00 3,600.00
2 laborer 4.00 da

Deadline: 2023-05-03